A Process Safety Framework for Reducing Operational Hazards During Facility Modifications, Equipment Replacement, and Commissioning
Susan Ochi Makut1, Festus-Michael Uwagboe2, Francis Ojeakhena3, Henry Chukwuemeka Olisakwe4
- 1
- 2
- 3
- 4
This is an author-deposited copy. The version of record was originally published elsewhere: Originally published in International Journal of Multidisciplinary Futuristic Development, Volume 4, Issue 2, 2023. DOI 10.54660/IJMFD.2023.4.2.78-98 . Original source: https://www.transdisciplinaryjournal.com/archives/year-2023.vol-4.issue-2.
Abstract
A disproportionate share of process safety incidents occurs during non-routine work: modifications, equipment replacement, tie-ins, start-up and commissioning. This study develops a quantified process safety framework for such work and applies it to a representative 28-activity brownfield project that replaces a separator, hot-taps a new compressor into a live header and upgrades a safety instrumented system. Each activity’s hazard rate is combined with the failure probabilities of its barriers. These probabilities rise with the number of simultaneous high-risk tasks and with proximity to live plant. Five framework elements were evaluated alone and in all 32 combinations: isolation management, risk-based permit to work, enhanced pre-startup review, safety instrumented system bypass management with start-up alarm rationalization, and contractor competence assurance. Inputs are representative literature values, not project data. Commissioning and start-up carried 61 percent of baseline risk, and start-up with bypassed protection alone carried 51 percent. Bypass management with alarm rationalization cut fatality-equivalent risk by 58 percent at a net saving. Four low-cost elements together cut it by 78 percent at roughly zero net cost after avoided incident costs. Adding all five reached 80 percent and reduced peak daily risk by 92 percent. Risk-aware scheduling added only 2 to 4 percent at the assumed concurrency effect, but 24 percent when that effect was quadrupled. Bypass management ranked first in 93 percent of uncertainty samples.
Keywords: process safetynon-routine operationscommissioningstart-uppermit to worksimultaneous operationssafety instrumented system bypass
Full text
Text extracted from the article PDF for reading and search. Tables, figures and equations are in the PDF, which remains the authoritative version.
1. Introduction
Process plants are most dangerous when they are changing. Analyses of incident databases show that a large share of process safety incidents occurs during maintenance, modification, shutdown and start-up rather than during steady operation [1–3]. The United States Chemical Safety and Hazard Investigation Board has devoted a safety digest to incidents during start-ups and shutdowns [2], the Environmental Protection Agency has issued an enforcement alert on the risk of chemical accidents during process start-up [4] and the Center for Chemical Process Safety has published guidelines for process safety during transient operating modes [3]. Studies of maintenance-related major accidents in the 21st century [5], maintenance as a source of major accidents in petroleum process plants [6] and the root causes of hydrocarbon leaks on offshore installations [7] show that work on equipment is a recurring trigger of loss of containment. The Piper Alpha disaster of 6 July 1988, in which a pump was restarted while its pressure safety valve had been removed under a permit that was not communicated across shifts, remains the defining example [8].
The hazards of non-routine work arise from the combination of several conditions that are absent in steady operation. Isolations must be made and verified before equipment is opened [9, 10]; permits to work must control hot work, line breaking, confined space entry and lifting near live plant [11– 13]; simultaneous operations (SIMOPS) place construction crews close to hydrocarbon systems [14, 15]; new equipment must be checked by pre-startup safety review (PSSR) before hydrocarbons are introduced [16, 17]; and safety instrumented systems (SIS) are often bypassed during commissioning and start-up and not always restored [18, 19]. Alarm floods during start-up overwhelm operators at the moment when their response matters most [20–22]. Investigations of the Formosa Plastics vinyl chloride explosion of 23 April 2004 [23], the Williams Geismar reboiler rupture of 13 June 2013 [24], the Esso Longford gas plant accident of 25 September 1998 [25] and the BP Texas City isomerization unit start-up of 23 March 2005 [26] illustrate how these conditions combine. Guidance exists for each element of control, but the elements are rarely evaluated together in a quantified way that shows which ones matter most for a given project and how they interact with the schedule. Process hazard analysis methods such as HAZOP and layer of protection analysis (LOPA) are typically applied to the steady-state design [27–29], and dynamic risk assessment methods have been developed mainly for operations rather than for projects [30–32]. Studies of permit-to-work effectiveness [33–35], lockout and tagout [36– 38], confined spaces [39, 40], turnaround management [41–43] and contractor safety [44–47] each address part of the problem. This paper develops and demonstrates a quantified process safety framework for modifications, equipment replacement and commissioning. It makes four contributions. First, it represents a brownfield project as a network of activities whose hazard rates and barrier failure probabilities depend on activity type, SIMOPS concurrency and proximity to live plant, producing a daily risk profile. Second, it evaluates five framework elements individually and in all combinations for risk reduction, cost and schedule effect. Third, it applies risk-aware scheduling to reduce concurrency of high-risk tasks. Fourth, it tests the robustness of the conclusions to parameter uncertainty. Section 2 reviews the literature, Section 3 describes the framework and model, Section 4 presents results, Section 5 discusses implications and Section 6 concludes.
2. Literature Review
This section reviews the evidence on incidents during non-routine operations, hazard identification and risk assessment methods, permit to work and isolation, SIMOPS and construction near live plant, start-up, commissioning and alarm management, safety instrumented systems during non-routine work, human and organizational factors in maintenance, dynamic risk and resilience, and turnaround planning. It draws on accounts of why major accidents continue to occur [48, 49] and on the history of process safety [50], which emphasize that the lessons of past accidents are repeatedly forgotten [51, 52]. It also reflects regulatory perspectives on human factors and major hazards [53, 54], root-cause and thematic analysis of major incidents [55], conceptual accounts of human error causation in high-risk construction and industrial activities [56] and trends in international process safety research [57].
2.1. Incidents During Non-Routine Operations
Incident analyses consistently identify maintenance, start-up and shutdown as high-risk phases. The hazards of transient operations have been reviewed [1], and incidents that define process safety include many in these phases [58]. Analyses of maintenance management deficiencies [59], maintenance-induced accidents and piping problems [60], maintenance safety management in the chemical industry [61], ageing assets at Dutch major hazard sites [62], accidents triggered by electrical failures [63], LPG loading and unloading [64] and common causes of major losses in onshore oil, gas and chemical facilities [65] add detail. Statistical analyses of incident databases in Greece [66, 67], France [68], South Korea [69, 70], China [71–78], Sri Lanka [79], the fuel ethanol industry [80], chemical plants and transport [81] and wastewater facilities [82, 83] reveal recurring contributors, including equipment failures [84, 85], process safety management element failures [86], corrective actions [87], hierarchy of controls in CSB reports [88] and key issues in accident reports [89]. Data mining and text analysis of incident databases [90–94], failure knowledge databases [95], reactive chemistry incidents [96], shutdowns and management of change [97–99], accident precursors [100], relationships between major hazard and occupational accidents [101], accident frequency prediction [102], occupational risks in maintenance [103], ergonomics in petrochemical maintenance [104], the Tianjin Port explosion [105], the Dalian tank farm fire [106], the Buncefield explosion [107], the Deepwater Horizon blowout [108], comparisons of major industrial disasters [109], management and technical factors [110], learning from major accidents for design [111] and design life cycle accident prevention [112] complete the picture. Hot work remains a leading cause of fatalities in and around tanks [113, 114], and mechanical sparks are an ignition source [115]. Near-miss and hazard observation data can reveal these contributors before they produce an accident [116], provided that proactive hazard recognition and reporting systems are in place to capture them [117].
2.2. Hazard Identification and Risk Assessment
HAZOP is the principal hazard identification method in process plants [29], and research has sought to improve it [27], automate it [118–122], combine it with dynamic simulation [123, 124], apply it to oil production units [125], fuel terminals [126], health, safety and environment engineering [127], multi-criteria decision making [128], reactors [129, 130], and FMEDA integration [131]. LOPA determines whether protection layers are sufficient [28, 132–134], often combined with HAZOP and SIL determination [135]. Bow-tie methods [136–138], baseline risk assessment tools [139], semi-quantitative prioritization [140], generic leak frequencies [141], risk assessment of aromatic units [142], risk assessment of construction during operation [143] and power plant construction risk [144] extend the toolkit. Risk-based process engineering frameworks have been proposed to strengthen reliability across natural gas infrastructure systems [145], and hazard identification and risk control practices in construction projects have been reviewed systematically [146]. Few of these methods are applied specifically to the sequence of activities in a modification project.
2.3. Permit to Work, Isolation and Confined Spaces
Permit-to-work systems are the main administrative barrier for non-routine work. Guidance from the UK Health and Safety Executive [11], reviews of permits in the process industries [12], offshore approaches [147, 148], transaction processing [149], effectiveness narratives [33], efficiency indicators [34], performance questionnaires [35], their contribution to accidents [13], lessons from incidents [150], safety management integration [151], human factors in control of work [152, 153] and digital transformation [154] have been studied. Isolation of hazardous energy through lockout and tagout is regulated [10] and has been studied in terms of fatal injuries [37], standard effects [155], situation awareness [36], alternative methods [156, 157], verification [158], self-audit tools [159, 160], written programmes [161], procedures [38], moving-parts accidents [162] and sawmills [163]. Confined space entry is regulated [164, 165] and has been studied for contributory factors [40, 166, 167], incident rates [168], rescue [169–171], comprehensive management [39, 172, 173], holistic approaches [174] and fatality surveillance [175]. Sharing awareness among maintenance crews [176] and the gap between safety documents and worker perception [177] show the limits of paperwork alone.
2.4. Simultaneous Operations, Construction Near Live
Plant and Contractors SIMOPS risk assessment has been developed for industrial sites [14], LNG bunkering [178], process plant expansions on operating sites [15] and construction activities during operation [143]. Contractors carry out much of the work in modifications and turnarounds, and their role in process safety [44], PSM for managing contractors [45], governance-oriented models of contractor safety performance in multi-contract projects [47], safety risk governance in multi-contractor projects [179], institutionalizing life-preserving safety practices across project-based organizations [180], interorganizational complexity [181] and European lessons on accidents involving contractors [46] have been examined. Risk pathway and risk management models have also been proposed for lifting and rigging in heavy industrial construction [182] and for heavy lifting and crane installation [183], operations that recur in equipment replacement. Organizational models integrating human factors and safety management [184–187], organizational and human factors in quantitative risk analysis [188], behavioural safety and major hazards [189], systems thinking and reliability culture [190], high reliability principles [191], organizational learning [192–194], management safety walkthroughs [195], near-miss archives [196], investigation guidelines [197], catastrophic incident warning signs [198] and internal audits [199, 200] provide the organizational context.
2.5. Start-Up, Commissioning and Alarm Management
Start-up concentrates hazards. Loss prevention at the start-up stage [17], PSSR performance and close-out [16], frameworks for managing transitions [201], and start-up procedures in novel plants [202] have been studied. Alarm management is critical during transitions, with surveys and reviews [203–205], lifecycle management [206], rationalization and suppression [207, 208], chatter quantification [209], dynamic strategies for transitions [21], chronicle-based management in start-up and shutdown [20], temporal pattern learning [210], diagnosis [211], superalarms [212], flood reduction [22], alarm database analysis [213, 214] and simulation of operator behaviour [215]. Operator training simulators [216, 217], workforce safety training models [218], virtual reality [219, 220], performance indicators [221], situation awareness [222–224], operator efficiency [225], decision support including human factors [226] and the reasons control systems fail [227] bear on start-up performance.
2.6. Safety Instrumented Systems During Non-Routine
Work Functional safety standards IEC 61508 and IEC 61511 govern SIS design and management, including management of bypasses and modifications [228–230]. Reliability data [231], reliability models [232], loss of safety assessment [233], new protection layers [234], SIL determination and calculation [235], multiphase dynamic Bayesian networks [236], cascading failures [237], reachability-based architecture assessment [238], testing strategies for final elements [239, 240], degradation [241], condition-based activation [242], demand-caused failures [243], partial tests [244], demand rate and imperfect proof tests [245], Markov simplifications [246], requirements for operation and maintenance [19], proof testing as a key performance indicator [247], maintenance on safety systems under change management [248] and the prevalence of undetected bypasses [18] show that SIS integrity depends on how bypasses and tests are managed during non-routine work.
2.7. Human Factors in Maintenance and Modification
Human error in maintenance has been reviewed [249–251] and studied in power plants [252], petroleum facilities [253], factories [254] and safety-critical organizations [255]. Human reliability analysis methods have been mapped [256] and reviewed for application [257], linked to task analysis [258], extended with Bayesian networks [259], applied to maintenance [260] and construction critical controls [261], and supported by guidance on safety critical task analysis [262, 263], qualitative human reliability assessment [264] and human factors assessment techniques [265, 266]. HFACS and related models have been applied to chemical accidents [267–274], and systemic accident models such as STAMP and 24Model have been compared [275–277]. Conceptual models of incident prevention in industrial maintenance environments [278], the recurrence mechanisms of unsafe behaviours in high-hazard worksites [279] and behavioural safety programmes for large workforces [280] address the same problem from the organizational side. Activity theory [281], normal accidents in refineries [282] and Korean PSM experience [283] complete the picture.
2.8. Dynamic Risk, Resilience and Maintenance Planning
Dynamic risk management updates risk as conditions change [30, 31, 284, 285], using real-time analysis of safety systems [32], Bayesian updating [286], multistate Bayesian networks for barrier degradation [287], managed pressure drilling [288], dynamic economic risk [289], digital twins [290] and continuous hazard monitoring systems [291]. Risk-based maintenance has been applied to power plants [292], gas regulating stations [293, 294], offshore processing [295] and maintenance scheduling [296], and risk assessment in maintenance decisions has been reviewed [297], as have Bayesian networks for inspection and maintenance [298]. Resilience engineering [299–301] has been applied to process systems [302–309], loss of containment prediction [310], health and safety management [311], Natech accidents [312] and barrier management [313], and reliability engineering faces new challenges [314]. Turnaround maintenance has been studied for practices [41], integration [42], scheduling [43] and spare parts [315], and a computerized maintenance management system (CMMS) concept has been proposed for optimizing preventive and corrective maintenance of static mechanical equipment [316]. Holistic control of process safety risks [317], global regulations [318], asset integrity [319], reliability and integrity management of fired heaters, boilers and furnaces in upstream oil and gas [320] and reliability-centred design of mechanical components using FEA and DFMEA [321] provide additional context.
2.9. Research Gap
The literature provides strong evidence that non-routine work concentrates risk and offers methods for each barrier, but it rarely quantifies the risk of a modification project activity by activity, evaluates combinations of controls against cost and schedule, or uses scheduling as a risk control [1, 14, 43]. Risk-based maintenance scheduling has been proposed for operating plants [295, 296], and SIMOPS assessments have been developed qualitatively [14], but the joint effect of barrier quality, concurrency and sequencing on the risk profile of a project has not been demonstrated. The framework presented next addresses this gap by combining an activity-level risk model with control elements whose effects can be compared on a common scale of risk, cost and schedule, and by treating the sequence of work itself as a control.
3. Framework and Methods
This section describes the framework, the representative project, the activity risk model, the framework elements, the economic evaluation, the risk-aware scheduling method and the uncertainty analysis. The risk model follows the logic of LOPA and bow-tie analysis, in which the frequency of a consequence is the initiating event frequency multiplied by the probabilities of failure of independent protection layers [28, 133, 136], extended so that barrier failure probabilities depend on the conditions of each project day, in the spirit of dynamic risk assessment [30, 31, 287] and of data-driven occupational safety risk control in large energy infrastructure projects [322]. All parameter values are representative values chosen within ranges reported in the literature cited; they are not data from a specific project, and the results demonstrate the framework and the relative value of its elements rather than estimate the risk of any particular project.
3.1. Framework Structure
Figure 1 shows the framework. A modification project passes through six phases: preparation, removal, installation, tie-in, testing, and commissioning and start-up. Five control elements act across these phases: integrated isolation management with independent verification (E1), a risk-based permit to work with a SIMOPS matrix (E2), enhanced PSSR and commissioning readiness with helium leak testing (E3), SIS bypass management and start-up alarm rationalization (E4), and contractor competence assurance and supervision (E5). A quantification layer converts activity hazards and barrier performance into a daily risk profile, and a sixth element, risk-aware scheduling (E6), re-sequences work to reduce the concurrency of high-risk tasks. The elements correspond to recognized good practice for isolation [9, 10], permits [11, 12], start-up readiness [16, 17], SIS and alarm management [18, 207, 230] and contractor management [44, 45].
Fig 1: Process safety framework for modifications, equipment replacement and commissioning: project phases, control elements and quantification layer.
3.2. Representative Project
The project replaces a separator, installs a new compressor skid tied into a live gas header by a hot tap, and replaces the SIS cabinet, at an operating onshore facility. It comprises 28 activities in three areas: area A, the compressor area adjacent to live plant; area B, the separator area; and area C, the control room and equipment room (Table 1). Durations range from one to six days and the earliest-start schedule takes 32 days. The activity types reflect the operations whose hazards are documented in the literature, including isolation and purging [9, 99], line breaking [60], hot work [113, 114], crane lifts near live equipment [15, 183], hot tapping [24], pressure testing, SIS testing [247], hydrocarbon introduction and start-up [2, 3].
Table 1: Activities of the representative brownfield project. No. Activity Area Type Duration (d) Predecessors 1 Isolation planning and permit set-up C admin 2 None
7 Disconnect separator piping B line_break 2 3, 5
8 Remove old separator by crane B lift 1 7 9 Cut out old piping B hot_work 3 7
10 Remove old control panels C electrical 2 1
11 Set new separator by crane B lift 1 8 12 Weld new separator piping B hot_work 6 9, 11 13 Set new compressor skid by crane A lift 1 6 14 Weld compressor piping near live plant A hot_work_live 6 13 15 Install new SIS cabinet and wiring C electrical 5 10 16 Install field instruments and cables B electrical 4 12, 14 17 Hot tap tie-in to live header A hot_tap 1 4, 14 18 Tie-in separator to process piping B line_break 2 12 19 Hydrotest separator piping B pressure_test 2 18 20 Hydrotest compressor piping A pressure_test 2 17 21 Leak test and reinstate flanges A line_break 2 19, 20 22 Loop checks and SIS site acceptance test C functional_test 4 15, 16 23 Pre-startup safety review C admin 2 21, 22 24 De-isolate and nitrogen purge B purge 1 23 25 Introduce hydrocarbons to separator B hc_intro 1 24 26 Start new compressor and ramp up A startup 2 25 27 Remove SIS bypasses and proof test C sis_proof 1 26 28 Handover to operations C admin 1 27
3.3. Activity Risk Model
For activity ?????? of type ?????? on day �, the frequency of a serious incident is the initiating event frequency multiplied by the failure probabilities of the barriers relevant to that type:
where ???????????? is the initiating event frequency per activity-day, ???????????? is the set of barriers, and �� is the probability of failure on demand of barrier �, which depends on the set of framework elements ??????, the SIMOPS concurrency �??????,?????? and the area �??????. For barriers whose effectiveness depends on the surrounding work, namely SIMOPS control, gas testing, fire watch and exclusion zones, the failure probability increases with concurrency and with proximity to live plant:
where ???????????? is the set of days on which activity ?????? is performed, ?????? is the expected number of serious incidents and PLL is the potential loss of life in fatality equivalents. Table 2 lists the parameters. During start-up the SIS is assumed to be bypassed with probability 0.5 without bypass management, consistent with reports that bypasses frequently remain in place undetected [18, 19]; with E4 this falls to 0.05.
Table 2: Activity hazard parameters: initiating events per activity-day, barriers with base failure probabilities, and fatality equivalents per serious incident.
Activity type Initiating events per day Barriers and base failure probabilities Fatality equivalent Isolation 0.006 isolation verification 0.1; permit 0.1 0.10 Purging 0.006 gas test 0.05; permit 0.1 0.10 Line breaking 0.012 isolation integrity 0.05; gas test 0.05; permit 0.1 0.15 Hot work 0.020 gas test 0.05; SIMOPS control 0.1; fire watch 0.2 0.20 Hot work near live plant 0.030 gas test 0.05; SIMOPS control 0.2; fire watch 0.2 0.25 Crane lift 0.004 lift plan 0.1; exclusion zone 0.2 0.30 Work at height 0.004 fall protection 0.05 0.20 Electrical work 0.002 lockout 0.05 0.20 Hot tap 0.040 hot tap procedure 0.05; pressure monitoring 0.1 0.30 Pressure test 0.004 exclusion zone 0.1; test procedure 0.1 0.20 SIS functional test 0.004 bypass management 0.2 0.10 Hydrocarbon introduction 0.060 PSSR line-up check 0.3; leak test 0.3; operator response 0.3 0.25 Start-up 0.040 SIS active 0.5 (bypass unmanaged); operator response 0.2 0.30 SIS bypass removal and proof test 0.006 test procedure 0.1 0.10
3.4. Framework Elements
Table 3 defines the effect of each element on barrier failure probabilities and its cost per project. E1 reduces isolation verification and integrity failures by 70 percent and gas test failures by 50 percent, reflecting independent verification of isolations [36, 38, 158]. E2 halves permit failures and reduces the SIMOPS degradation factor from 0.5 to 0.2 by prohibiting incompatible concurrent tasks [11, 14, 34]. E3 reduces PSSR line-up failures by 60 percent and leak-test failures by 70 percent through structured readiness reviews and helium leak testing of new joints, at the cost of one day [16, 17]. E4 reduces the probability that the SIS is bypassed during start-up from 0.5 to 0.05, halves operator response failures during hydrocarbon introduction and start-up through alarm rationalization, and reduces bypass management failures during SIS testing by 70 percent [18, 20, 207]. E5 reduces the failure probability of all barriers that depend on human performance by 30 percent through competence assurance and supervision [44, 45, 47]. Costs are marginal per-project costs; schedule extension is valued at USD 0.15 million per day of deferred production, and avoided serious incidents at USD 20 million each, including repair, response and lost production.
Table 3: Framework elements, their effects in the model and their cost per project. Element Effect on barrier failure probabilities Cost per project (USD M)
Schedule effect E1 Isolation management with independent verification Isolation verification and integrity x 0.3; gas test x 0.5 0.08 None E2 Risk-based permit to work with SIMOPS matrix Permit x 0.5; SIMOPS degradation factor 0.5 to 0.2 0.05 None E3 Enhanced PSSR and readiness with helium leak testing PSSR line-up x 0.4; leak test x 0.3 0.15 One day E4 SIS bypass management and start-up alarm rationalization SIS bypassed at start-up 0.5 to 0.05; operator response x 0.5; bypass management x 0.3 0.06 None E5 Contractor competence assurance and supervision Human-dependent barriers x 0.7 0.12 None
3.5. Risk-Aware Scheduling and Uncertainty Analysis
Risk-aware scheduling (E6) delays the start of activities beyond their earliest start, within their float and an allowed extension of the project, to reduce concurrency. The delays were optimized by simulated annealing over integer start-day offsets, minimizing PLL subject to the precedence constraints and a maximum project duration, a heuristic approach consistent with turnaround scheduling practice [43, 296, 315]. Extensions of 0, 2 and 4 days were evaluated, and the value of scheduling was tested for SIMOPS degradation factors from 0.25 to 2.0. Parameter uncertainty was assessed by multiplying each initiating event frequency by an independent lognormal factor with an error factor of 3 and each barrier failure probability by a factor with an error factor of 2, and drawing 1,000 samples; for each sample the baseline and full-framework risks and the element giving the largest single risk reduction were recorded [286, 287, 289].
4. Results
This section reports the baseline risk profile and its sources, the effects of individual elements and their combinations, the effect of risk-aware scheduling and the robustness of the results to parameter uncertainty. Because the inputs are representative, the distribution of risk across phases and the ranking of elements are more informative than absolute values, consistent with the use of LOPA and bow-tie quantification for comparing options rather than predicting outcomes [133, 136]. The baseline corresponds to execution of the earliest-start schedule with the base barrier probabilities in Table 2 and none of the framework elements. All comparisons use the same activity network and parameter values, so differences between cases reflect only the elements and schedules applied.
4.1. Baseline Risk Profile
The baseline project had an expected 0.020 serious incidents and a PLL of 4.68 x 10-3 fatality equivalents over 32 days. Figure 2 shows the daily risk profile. Risk was low during preparation and removal, rose during installation when hot work near live plant coincided with other high-risk tasks in area A, and peaked sharply during start-up on days 28 and 29, at 1.2 x 10-3 per day, about sixteen times the average daily risk of the installation phase. By phase, commissioning and start-up accounted for 61 percent of PLL, installation for 22 percent, testing for 8 percent, preparation for 5 percent, removal for 3 percent and tie-in for 1 percent. Figure 3 shows the contributions by activity type: start-up with a 50 percent chance of bypassed SIS protection accounted for 51 percent of PLL, hot work near live plant for 16 percent, hydrocarbon introduction for 9 percent and SIS functional testing for 7 percent. Isolation, purging and line breaking, each protected by two or three barriers, contributed less than 1 percent together. This concentration in start-up reflects the CSB and EPA findings on start-up incidents [2, 4] and the Texas City experience [26].
Fig 2: Daily fatality-equivalent risk over the project for baseline execution, the framework elements E1 to E5, and the framework with risk-aware scheduling.
Fig 3: Fatality-equivalent risk per project by activity type for baseline execution and with framework elements E1 to E5.
4.2. Framework Elements and Combinations
Table 4 reports the effects of individual elements and selected combinations, and Figure 4 shows all 32 combinations. SIS bypass management with start-up alarm rationalization (E4) was by far the most effective single element, reducing PLL by 58 percent and serious incidents by 53 percent for USD 0.06 million, a net saving of USD 0.15 million after avoided incident costs. Contractor competence assurance (E5) reduced PLL by 28 percent. Isolation management (E1), risk-based permits (E2) and enhanced PSSR (E3) each reduced PLL by 8 to 9 percent; E3 was the least cost-effective because it extended the schedule. The cost-efficient frontier rose steeply to E4, then to E2 with E4 (66 percent reduction), E1, E2 and E4 (71 percent) and E1, E2, E4 and E5 (78 percent, at a net cost of USD 0.02 million after avoided incidents). Adding E3 to these four raised the reduction to 80 percent at a further USD 0.30 million. With all five elements, the peak daily risk fell from 1.2 x 10-3 to 1.0 x 10-4, a 92 percent reduction, and the risk profile became nearly flat (Figure 2), with installation rather than start-up the largest remaining phase. These results support the emphasis on SIS bypass control in functional safety standards [228, 230] and on barrier management during transient operations [3, 287].
Table 4: Effects of framework elements and selected combinations. Elements PLL (x 10-3)
Serious incidents Duration (d)
Net cost after avoided incidents (USD M)
Cost per serious incident averted (USD M)
4.3. Risk-Aware Scheduling
Risk-aware scheduling had a modest effect at the assumed SIMOPS degradation factor. Without the framework elements, rescheduling within the 32-day duration reduced PLL by 3.7 percent, mainly by separating hot work near live plant from other high-risk tasks in area A. With all framework elements, which already include the SIMOPS matrix, rescheduling reduced PLL by 1.9 percent at no extension and by 3.1 and 3.6 percent with extensions of 2 and 4 days, and it reduced the peak daily risk of the project by 19 percent. The value of scheduling depends strongly on how much concurrency degrades barriers (Figure 5b): for degradation factors of 0.25, 0.5, 1.0 and 2.0 per concurrent task, rescheduling without extension reduced PLL by 1.4, 3.4, 9.5 and 24.4 percent. Where SIMOPS interactions are strong, as in congested brownfield sites [14, 15], sequencing becomes a significant control.
4.4. Robustness to Parameter Uncertainty
Figure 5a shows the effect of parameter uncertainty. The baseline PLL had a median of 5.8 x 10-3 with a 90 percent range from 2.8 x 10-3 to 14.7 x 10-3, and the full framework a median of 1.3 x 10-3 with a range from 0.7 x 10-3 to 2.3 x 10- 3. The relative reduction ranged from 62 to 90 percent with a median of 79 percent, so the framework reduced risk substantially across the plausible range. E4 gave the largest single-element reduction in 93 percent of samples, E5 in 4 percent and E1 in 3 percent, so the priority of SIS bypass management and start-up alarm rationalization is robust to the uncertainty in the inputs [286, 287].
Fig 5: (a) Fatality-equivalent risk per project under parameter uncertainty for baseline and framework (box shows quartiles, whiskers 5th and 95th percentiles) and (b) risk reduction from risk-aware scheduling as a function of the SIMOPS degradation factor.
5. Discussion
This section interprets the findings, draws implications for project and operations teams, considers how the framework can be applied to real projects and sets out the limitations of the study. The discussion is framed by the observation that major accidents continue to occur during non-routine work despite long-established guidance [48, 50, 51], and by the systems view that the controls for such work are interdependent barriers rather than separate procedures [136, 137, 184]. It also considers how the findings relate to the organizational conditions, such as contractor management and learning from incidents, on which the effectiveness of every control depends [44, 192].
5.1. Principal Findings
Three findings stand out. First, the risk of a modification project is concentrated in time and in a few activities. In the representative project, the two start-up days carried more than half of the project’s fatality-equivalent risk, and the start-up peak was about sixteen times the average daily risk of installation. This concentration matches incident evidence that start-up and other transient operations generate a disproportionate share of serious process safety events [1, 2, 4], and it implies that controls should be targeted at the transition from construction to operation rather than spread evenly across the project.
Second, the most valuable control in the model was not a work control such as permits or isolation but the management of SIS bypasses and alarms during start-up. Because the SIS is the last automated barrier and its bypass during commissioning removes it entirely, restoring it before hydrocarbons are introduced removed more risk than any other element and paid for itself through avoided incidents. This reflects reports that bypassed protection is common and often undetected [18], the requirements of IEC 61511 for bypass management [230] and the role of alarm floods in start-up incidents [20, 21]. Isolation, permits and contractor competence remained valuable, particularly for the hot work near live plant that dominated installation risk, and four low-cost elements together cut risk by 78 percent at roughly zero net cost.
Third, scheduling is a conditional control. At a moderate concurrency effect, re-sequencing work reduced risk by only a few percent once a SIMOPS matrix was in place, but when concurrency degraded barriers strongly, re-sequencing reduced risk by a quarter. The value of risk-aware scheduling therefore depends on site congestion and the strength of SIMOPS interactions, which are rarely quantified in practice [14, 15].
5.2. Implications for Practice
For project and operations teams, the results suggest a sequence of actions. The first is to build a daily risk profile for each modification project from its activity schedule, using the barrier logic of LOPA and bow-tie analysis [28, 136, 138], so that high-risk days are visible before work begins. The second is to treat SIS bypass management, start-up alarm rationalization and operator readiness as a commissioning deliverable with the same status as mechanical completion [19, 207, 216]. The third is to apply risk-based permits with an explicit SIMOPS matrix and independent verification of isolations, which are inexpensive and reduce risk across all phases [11, 34, 36]. The fourth is to assure the competence of contractors who perform hot work, lifting and tie-ins near live plant [44–46]. The fifth is to use scheduling to separate high-risk tasks where the site is congested, especially hot work near live plant, so that productivity is balanced against safety compliance rather than traded for it [15, 43, 323]. For organizations, the framework provides a basis for learning across projects. Incident databases and investigation reports can be used to calibrate initiating event frequencies and barrier failure probabilities by activity type [66, 80, 90], near-miss archives can reveal barrier degradation [116, 196], and dynamic risk tools, continuous hazard monitoring and digital twins can update the daily profile as work progresses [31, 290, 291]. Human factors critical task analysis can strengthen the human-dependent barriers that dominate several activity types [262–264].
5.3. Application to Real Projects
The framework requires an activity schedule with areas and activity types, a library of initiating event frequencies and barrier failure probabilities, and estimates of SIMOPS interactions. Generic leak frequencies [141], SIS reliability data [231], human reliability methods [256, 257, 259] and incident statistics [84, 85] can supply initial values, and Bayesian updating can refine them as site experience accumulates [286, 287]. Dependencies between barriers, such as shared reliance on the same supervisor or permit, can be represented with Bayesian networks [268, 269] or STAMP-based analyses [277]. For turnarounds with hundreds of activities, the scheduling heuristic can be replaced by constraint programming or mixed-integer formulations used in turnaround scheduling [43, 315].
5.4. Limitations
The study has several limitations. All parameters are representative values rather than data from a specific project, so absolute risks should not be transferred without calibration. Barriers were treated as independent, which overstates the benefit of layering where common causes such as fatigue or supervision failures affect several barriers at once [184, 188]. The effects of framework elements were represented as fixed multipliers on barrier failure probabilities, whereas their real effectiveness depends on implementation quality and culture [189, 191]. The SIMOPS model used a simple linear degradation with concurrency, and the value of scheduling is sensitive to it. Consequences were expressed as fatality equivalents and an average incident cost, without modelling escalation to neighbouring units. Finally, the model covers a single project; organizational learning across projects, which could change barrier performance over time, was not represented [192, 194, 324].
6. Conclusion
This study developed a quantified process safety framework for modifications, equipment replacement and commissioning, combining an activity-level risk model, five control elements and risk-aware scheduling, and applied it to a representative brownfield project at an operating facility. The risk of the project was concentrated in commissioning and start-up, and above all in starting new equipment with safety instrumented protection bypassed. Managing those bypasses and rationalizing start-up alarms removed more than half of the project’s risk at a net saving, and together with isolation management, risk-based permits with a simultaneous-operations matrix and contractor competence assurance reduced risk by about four fifths at roughly zero net cost. Enhanced pre-startup review added a further reduction at higher cost. Risk-aware scheduling added little where concurrency effects were moderate but became significant where they were strong. The priority of bypass management held across the range of parameter uncertainty. For facilities planning modifications, the results support building a daily risk profile for each project, treating safety system and alarm readiness as a commissioning deliverable, applying risk-based permits and independent isolation verification throughout, assuring contractor competence and using scheduling where sites are congested. Further work should calibrate the framework with incident and project data, represent dependencies between barriers and extend it to multi-project turnarounds.
References
- Center for Chemical Process Safety. Guidelines for process safety during the transient operating mode: Managing risks during process start-ups and shut-downs. John Wiley & Sons; 2021.
- U.S. Environmental Protection Agency. Risk of chemical accidents during process startup (Enforcement Alert, EPA Document No. 300N21002). Office of Enforcement and Compliance Assurance, U.S. Environmental Protection Agency; 2021.
- Okoh P, Haugen S. A study of maintenance-related major accident cases in the 21st century. Process Safety and Environmental Protection. 2014;92(4):346-356.
- Vinnem JE, Haugen S, Okoh P. Maintenance of petroleum process plant systems as a source of major accidents?. Journal of Loss Prevention in the Process Industries, 40, 348-356. 2016.
- Public Inquiry into the Piper Alpha Disaster. (1990). The public inquiry into the Piper Alpha disaster (Vols. 1-2). HMSO, London.
- Center for Chemical Process Safety. Guidelines for safe process operations and maintenance. American Institute of Chemical Engineers; 1995.
- Occupational Safety, Health Administration. Control of hazardous energy: Lockout/tagout (OSHA 3120). U.S. Department of Labor; 2002.
- Health, Safety Executive. Guidance on permit-to-work systems: A guide for the petroleum, chemical and allied industries (HSG250). HSE Books; 2005.
- Gould J. Permits-to-work in the process industries. Loss Prevention Bulletin. 2007;198:6.
- Canaway, R. (2021). Assessing the risks when expanding process plants or building new units on compact sites. Hazards 31, IChemE Symposium Series No. 168.
- Di Vito F. Pre-startup safety review performance and close-out management for a new licensed petrochemical plant. Chemical Engineering Transactions. 2020;82:25-
- Marszal, E., & Hughes, M. (2021). You have SIS bypassed right now and don’t know it. 2021 AIChE Virtual Spring Meeting and 17th Global Congress on Process Safety, Paper 143c.
- Vásquez, J. W., Travé-Massuyès, L., Subias, A., Jiménez, F., & Agudelo, C. (2015). Chronicle based alarm management in startup and shutdown stages. 26th International Workshop on Principles of Diagnosis (DX-2015), Paris, 277-280.
- Rodrigo V, Chioua M, Hagglund T, Hollender M. Causal analysis for alarm flood reduction. IFAC-PapersOnLine. 2016;49(7):723-728. doi:10.1016/j.ifacol.2016.07.269 https://doi.org/10.1016/j.ifacol.2016.07.269
- Chemical Safety US, Hazard Investigation Board. Investigation report: Vinyl chloride monomer explosion, Formosa Plastics Corp., Illiopolis, Illinois (Report No. 2004-10-I-IL). U.S. Chemical Safety and Hazard
- Chemical Safety US, Hazard Investigation Board. Case study: Williams Geismar olefins plant reboiler rupture and fire (Report No. 2013-03-I-LA). U.S. Chemical Safety and Hazard Investigation Board; 2016.
- Dawson D, Brooks B. The Esso Longford gas plant accident: Report of the Longford Royal Commission. Government Printer for the State of Victoria; 1999.
- Manca D, Brambilla S, Villa A. Increasing the understanding of the BP Texas City refinery accident. Computer Aided Chemical Engineering. 2011;29:1266-1270.
- Dowell, A. M., III. (1998). Layer of protection analysis for determining safety integrity level. ISA Transactions, 37, 155-165. Hazard and operability studies (HAZOP studies) - Application guide. IEC, Geneva; 2016.
- Villa V, Paltrinieri N, Cozzani V. Overview on dynamic approaches to risk management in process facilities. Chemical Engineering Transactions. 2015;43:2497-2502. doi:10.3303/CET1543417 https://doi.org/10.3303/CET1543417
- Paltrinieri, N., Khan, F. I., & Cozzani, V. (2014). Coupling of advanced techniques for dynamic risk management. Journal of Risk Research, 1-21. https://doi.org/10.1080/13669877.2014.919515 https://doi.org/10.1080/13669877.2014.919515
- Meel A, Seider WD. Real-time risk analysis of safety systems. Computers & Chemical Engineering. 2008;32(4-5):827-840. doi:10.1016/j.compchemeng.2007.03.006 https://doi.org/10.1016/j.compchemeng.2007.03.006
- Amm, H. (2021). Effectiveness of permit to work systems narrative. Human Systems Engineering and Design (IHSED 2021), AHFE Open Access.
- Abbasi S, Gilani N, Javanmardi M. Prioritizing the indicators influencing permit to work system efficiency based on an analytic network process. International Journal of Occupational Safety and Ergonomics; 2021.
- Mousavi S, Karimi A, Zakerian SA. Development and validation of work permit system performance assessment questionnaire, a case study in an Iranian oil refinery. Archives of Hygiene Sciences. 2019;8(3):154-162.
- Illankoon P, Manathunge Y, Tretten P, Abeysekara J, Singh S. Lockout and tagout in a manufacturing setting from a situation awareness perspective. Safety. 2019;5(2):25. doi:10.3390/safety5020025 https://doi.org/10.3390/safety5020025
- Bulzacchelli MT, Vernick JS, Sorock GS, Webster DW, Lees PSJ. Circumstances of fatal lockout/tagout-related injuries in manufacturing. American Journal of Industrial Medicine. 2008;51:728-734. doi:10.1002/ajim.20630 https://doi.org/10.1002/ajim.20630
- Chinniah Y, Burlet-Vienney D. Study on lockout procedures for the safety of workers intervening on equipment in the municipal sector in Quebec. International Journal of Occupational Safety and Ergonomics. 2013;19:495-511.
- Burlet-Vienney D, Chinniah Y, Bahloul A. The need for a comprehensive approach to managing confined space entry: Summary of the literature and recommendations for next steps. Journal of Occupational and Environmental Hygiene. 2014;11(8):485-498.
- Naghavi K Z, Mortazavi SB, Asilian M H, Hajizadeh E. Exploring the contributory factors of confined space accidents using accident investigation reports and semistructured interviews. Safety and Health at Work. 2019;10(3):305-313. doi:10.1016/j.shaw.2019.06.007 https://doi.org/10.1016/j.shaw.2019.06.007
- Duffuaa SO, Ben Daya MA. Turnaround maintenance in petrochemical industry: Practices and suggested improvements. Journal of Quality in Maintenance Engineering. 2004;10(3):184-190. doi:10.1108/13552510410553235 https://doi.org/10.1108/13552510410553235
- Duffuaa SO, Al-Turki UM, Ben Daya M. Status of integrated turnaround maintenance. 2019 Industrial and Systems Engineering Conference (ISEC 2019). IEEE. 2019;8686568. doi:10.1109/IASEC.2019.8686568 https://doi.org/10.1109/IASEC.2019.8686568
- Megow N, Möhring RH, Schulz J. Decision support and optimization in shutdown and turnaround scheduling. INFORMS Journal on Computing. 2011;23(2):189-204.
- Tamim N, Scott S, Zhu W, Koirala Y, Mannan MS. Roles of contractors in process safety. Journal of Loss doi:10.1016/j.jlp.2017.04.023 https://doi.org/10.1016/j.jlp.2017.04.023
- European Commission Joint Research Centre. Lessons learned bulletin No. 2: Major accidents involving contractors (Chemical accident prevention and preparedness series). Joint Research Centre, European Commission; 2012.
- Amyotte PR, Berger S, Edwards DW, Gupta JP, Hendershot DC, Khan FI, et al. Why major accidents are still occurring. Current Opinion in Chemical Engineering. 2016;14:1-8.
- Kletz TA. Lessons from disaster: How organizations have no memory and accidents recur. Institution of Chemical Engineers; 1993.
- Kletz TA. Learning from experience. Journal of Hazardous Materials. 2004;115:1-8.
- Anderson, M. (2003). Human factors and COMAH: A regulator’s perspective. Hazards XVII, IChemE Symposium Series, 785-792.
- Health, Safety Executive. Inspecting human factors at COMAH establishments (Operational Delivery Guide). Health and Safety Executive, UK; 2016.
- Okwesa IJ, Unamma UML, Iwuanyanwu U. Root-cause and thematic analysis for major incident management: A review. International Journal of Social Sciences and Management Research. 2021;7(4):100-131. doi:10.56201/ijssmr.v7.no4.2021.pg100.131 https://doi.org/10.56201/ijssmr.v7.no4.2021.pg100.131
- Li, J., Goerlandt, F., Reniers, G., Feng, C., & Liu, Y. (2022). Chinese international process safety research: Collaborations, research trends, and intellectual basis. Journal of Loss Prevention in the Process Industries, 74, 104657. https://doi.org/10.1016/j.jlp.2021.104657 https://doi.org/10.1016/j.jlp.2021.104657
- Atherton J, Gil F. Incidents that define process safety. Center for Chemical Process Safety, AIChE / Wiley; 2008.
- Smith, E. J., & Harris, M. J. (1992). The role of maintenance management deficiencies in major accident causation. Proceedings of the Institution of Mechanical Engineers, Part E: Journal of Process Mechanical Engineering, 206, 55-66.
- Sanders, R. E. (2005). Maintenance-induced accidents and process piping problems. Chemical process safety: Learning from case histories (3rd ed., pp. 91-123). Elsevier, 91-123.
- Hale AR, Heming BHJ, Smit K, Rodenburg FG, van Leeuwen ND. Evaluating safety in the management of maintenance activities in the chemical process industry. Safety Science. 1998;28(1):21-44.
- Hansler RJ, Bellamy LJ, Akkermans HA. Ageing assets at major hazard chemical sites - The Dutch experience. Safety Science. 2022;153:105788.
- Lloyd’s Market Association. An analysis of common causes of major losses in the onshore oil, gas and petrochemical industries. Lloyd’s Market Association; 2016.
- Konstandinidou M, Nivolianitou Z, Markatos N, Kiranoudis C. Statistical analysis of incidents reported in the Greek petrochemical industry for the period 1997-2003. Journal of Hazardous Materials. 2006;135(1-3):1-9.
- Dakkoune A, Vernières-Hassimi L, Leveneur S, Lefebvre D. Risk analysis of French chemical industry. Safety Science. 2018;105:77-85.
- Jung S, Woo J, Kang C. Analysis of severe industrial accidents caused by hazardous chemicals in South Korea from January 2008 to June 2018. Safety Science.
- Shin IJ. Major industrial accidents in Korea: The characteristics and implication of statistics 1996-2011. Process Safety Progress. 2013;32(1):90-95.
- Yang, J. F., Wang, P. C., Liu, X. Y., Bian, M. C., Chen, L. C., Lv, S. Y., et al. (2023). Analysis on causes of chemical industry accident from 2015 to 2020 in Chinese mainland: A complex network theory approach. Journal of Loss Prevention in the Process Industries, 83, 105061. https://doi.org/10.1016/j.jlp.2023.105061 https://doi.org/10.1016/j.jlp.2023.105061
- He, G., Zhang, L., Lu, Y., & Mol, A. P. J. (2011). Managing major chemical accidents in China: Towards effective risk information. Journal of Hazardous Materials, 187(1-3), 171-181.
- Zhou, J., Liu, L., Su, Y., Liang, R., Feng, J., & Wang, X. (2023). Statistical investigation on the characteristics of hazardous chemical accidents in special work in China from 2008 to 2021. Process Safety Progress. https://doi.org/10.1002/prs.12526 https://doi.org/10.1002/prs.12526
- Luo, X., Feng, X., Ji, X., Dang, Y., Zhou, L., et al. (2023). Extraction and analysis of risk factors from Chinese chemical accident reports. Chinese Journal of Chemical Engineering, 61, 68-81. https://doi.org/10.1016/j.cjche.2023.02.026 https://doi.org/10.1016/j.cjche.2023.02.026
- Wang, B., Li, D., & Wu, C. (2020). Characteristics of hazardous chemical accidents during hot season in China from 1989 to 2019: A statistical investigation. Safety Science, 129, 104788. https://doi.org/10.1016/j.ssci.2020.104788 https://doi.org/10.1016/j.ssci.2020.104788
- Duan, W., Chen, G., Ye, Q., & Chen, Q. (2011). The situation of hazardous chemical accidents in China between 2000 and 2006. Journal of Hazardous Materials, 186, 1489-1494.
- Vílchez JA, Sevilla S, Montiel H, Casal J. Historical analysis of accidents in chemical plants and in the transportation of hazardous materials. Journal of Loss Prevention in the Process Industries. 1995;8(2):87-96.
- Trávníček P, Junga P, Kotek L, Vítěz T. Analysis of accidents at municipal wastewater treatment plants in Europe. Journal of Loss Prevention in the Process Industries. 2022;74:104634.
- Kidam K, Hurme M. Analysis of equipment failures as contributors to chemical process accidents. Process Safety and Environmental Protection. 2013;91:61-78.
- Kidam K, Hurme M. Statistical analysis of contributors to chemical process accidents. Chemical Engineering & Technology. 2013;36:67-76.
- Hussin NAE, Kidam K, Johari A, Hashim H. Suitability analysis of corrective actions to prevent major chemical process accidents. Jurnal Teknologi (Sciences & Engineering). 2017;79(3):97-106.
- Amyotte PR, MacDonald DK, Khan FI. An analysis of CSB investigation reports concerning the hierarchy of controls. Process Safety Progress. 2011;30(3):261-265.
- Fyffe L, Krahn S, Clarke J, Kosson D, Hutton J. A preliminary analysis of key issues in chemical industry accident reports. Safety Science. 2016;82:368-373.
- Prem, K. P., Ng, D., & Mannan, M. S. (2010). Harnessing database resources for understanding the profile of chemical process industry incidents. Journal of Loss Prevention in the Process Industries, 23(4), 549-560.
- Anand S, Keren N, Tretter MJ, Wang Y, O’Connor TM, Mannan MS. Harnessing data mining to explore incident databases. Journal of Hazardous Materials. 2006;130:33-41.
- Yang S, Demichela M. A data-driven narratives skeleton pattern recognition from accident reports dataset for human-and-organizational-factors analysis. Journal of Loss Prevention in the Process Industries. 2023;83:105047. doi:10.1016/j.jlp.2023.105047 https://doi.org/10.1016/j.jlp.2023.105047
- Bellamy, L. J., Ale, B. J. M., Geyer, T. A. W., Goossens, L. H. J., Hale, A. R., Oh, J., Mud, M., Bloemhof, A., Papazoglou, I. A., & Whiston, J. Y. (2007). Storybuilder - A tool for the analysis of accident reports. Reliability Engineering & System Safety, 92, 735-744.
- Carpenter JK, Hendershot DC, Watts SJ. Learning from reactive chemistry incidents. Chemical Health and Safety. 2004;11(4):10-16.
- Malmén, Y., Nissilä, M., & Virolainen, K. (2011). Shutdowns and management of change. Hazards XXII, IChemE Symposium Series No. 156, 192-197.
- Hansen, M. D., & Gammel, G. W. (2008). Management of change: A key to safety - not just process safety. Professional Safety(October), 41-50.
- Malmén Y, Nissilä M, Repola P, Virolainen K. Process chemicals - An ever present concern during plant shutdowns. Journal of Loss Prevention in the Process Industries. 2010;23(2):249-252.
- Taylor RH, van Wijk LGA, May JHM, Carhart NJ. A study of the precursors leading to ‘organisational’ accidents in complex industrial settings. Process Safety and Environmental Protection. 2015;93:50-67.
- Bellamy LJ. Exploring the relationship between major hazard, fatal and non-fatal accidents through outcomes and causes. Safety Science. 2015;71:93-103.
- Attwood D, Khan F, Veitch B. Can we predict occupational accident frequency?. Process Safety and Environmental Protection, 84(3), 208-221. 2006.
- Lind S, Nenonen S. Occupational risks in industrial maintenance. Journal of Quality in Maintenance Engineering. 2008;14:194-204. doi:10.1108/13552510810877683 https://doi.org/10.1108/13552510810877683
- Bevilacqua M, Ciarapica FE, Giacchetta G. Industrial and occupational ergonomics in the petrochemical process industry: A regression trees approach. Accident Analysis & Prevention. 2008;40:1468-1479. doi:10.1016/j.aap.2008.03.012 https://doi.org/10.1016/j.aap.2008.03.012
- Chen, M., & Wang, X. (2012). Lessons learned from Dalian tank farm accident. 2012 AIChE Spring Meeting and 8th Global Congress on Process Safety, Houston, TX, 1825-1833.
- Buncefield Major Incident Investigation Board. (2008). The Buncefield incident 11 December 2005: The final report of the Major Incident Investigation Board (Vol. 1). HSE Books.
- Kidam K, Hussin NE, Hassan O, Ahmad A, Johari A, Hurme M. Accident prevention approach throughout process design life cycle. Process Safety and Environmental Protection. 2014;92:412-422.
- American Petroleum Institute. API RP 2009: Safe welding, cutting, and hot work practices in the petroleum and petrochemical industries (7th ed.). American Petroleum Institute; 2002.
- Arumosoye OM, Obriki OD. Systematic review of near-miss and hazard observation data utilization in industrial safety management. Iconic Research and Engineering Journals. 2019;3(2):981-999. doi:10.64388/IREV3I2-1714417 https://doi.org/10.64388/IREV3I2-1714417
- Obogo SF, Arumosoye OM, Obriki OD. Advances in proactive hazard recognition and near miss reporting systems. International Journal of Multidisciplinary Research and Growth Evaluation. 2021;2(6):835-846. doi:10.54660/IJMRGE.2021.2.6.835-846 https://doi.org/10.54660/IJMRGE.2021.2.6.835-846
- Single JI, Schmidt J, Denecke J. Ontology-based computer aid for the automation of HAZOP studies. 2020;68:104321. doi:10.1016/j.jlp.2020.104321 https://doi.org/10.1016/j.jlp.2020.104321
- Taylor JR. Automated HAZOP revisited. Process Safety and Environmental Protection. 2017;111:635-651.
- de Azevedo, J. P. A., de Souza, M. B., Jr., & Pinto, J. C. (2022). Process hazard analysis based on modeling and simulation tools. Processes, 10(2), 386. https://doi.org/10.3390/pr10020386 https://doi.org/10.3390/pr10020386
- Penelas, A. de J., Pires JCM. HAZOP analysis in terms of safety operations processes for oil production units: A case study. Applied Sciences. 2021;11(21):10210. doi:10.3390/app112110210 https://doi.org/10.3390/app112110210
- Fuentes-Bargues JL, González-Cruz MC, González-Gaya C, Baixauli-Pérez MP. Risk analysis of a fuel storage terminal using HAZOP and FTA. International Journal of Environmental Research and Public Health, 14(7), 705. 2017. doi:10.3390/ijerph14070705 https://doi.org/10.3390/ijerph14070705
- Choi JY, Byeon SH. HAZOP methodology based on the health, safety, and environment engineering. International Journal of Environmental Research and Public Health. 2020;17(9):3236. doi:10.3390/ijerph17093236 https://doi.org/10.3390/ijerph17093236
- Marhavilas PK, Filippidis M, Koulinas GK, Koulouriotis DE. A HAZOP with MCDM based risk-assessment approach: Focusing on the deviations with economic/health/environmental impacts in a process industry. Sustainability. 2020;12(3):993.
- Antonello F, DeDominicis D, Ivaldi A, Fiocca G, Tomiato L. Reliability analysis and risk analysis: Integration between Hazop, FMEDA and fault tree analysis for SIL assessment. Chemical Engineering Transactions. 2016;48:1-6. doi:10.3303/CET1648001 https://doi.org/10.3303/CET1648001
- Park B, Kim Y, Lee K, Paik S, Kang C. Risk assessment method combining independent protection layers (IPL) of layer of protection analysis (LOPA) and RISKCURVES software: Case study of hydrogen refueling stations in urban areas. Energies. 2021;14(13):4043. doi:10.3390/en14134043 https://doi.org/10.3390/en14134043
- Iddir O. Evolutions of the LOPA method to a fully quantified method. Process Safety Progress. 2023;42:290-298. doi:10.1002/prs.12446 https://doi.org/10.1002/prs.12446
- Wang, J., Hu, D., Peng, C., Zhi, H., & Wu, L. (2023). Safety assessment through HAZOP-LOPA-SIL analysis implementation in the DPA demulsifier production process. Process Safety Progress, 42, 38-47. https://doi.org/10.1002/prs.12414 https://doi.org/10.1002/prs.12414
- Center for Chemical Process Safety, Energy Institute. Bow ties in risk management: A concept book for process safety. Wiley-AIChE; 2018.
- de Ruijter A, Guldenmund F. The bowtie method: A review. Safety Science. 2016;88:211-218.
- Aust J, Pons D. A systematic methodology for developing bowtie in risk assessment: Application to borescope inspection. Aerospace. 2020;7(7):86. doi:10.3390/aerospace7070086 https://doi.org/10.3390/aerospace7070086
- Spouge J. New generic leak frequencies for process equipment. Process Safety Progress. 2005;24(4):249-257.
- Sarafraz P, Varshosaz K, Orak N, Jaafarzadeh N, Aghajari E. Safety, health, and environmental risk assessment of the aromatic outlet of Imam Khomeini Petrochemical Company using LOPA and fuzzy-LOPA and pollutants and control actions using the Bow-tie method. Frontiers in Public Health. 2023;11:1251548. doi:10.3389/fpubh.2023.1251548 https://doi.org/10.3389/fpubh.2023.1251548
- Sánchez Colmenarejo JI, Morales Camprubí F, González-Gaya C, Sánchez-Lite A. Power plant construction projects risk assessment: A proposed method for temporary systems of commissioning. Buildings. 2022;12(8):1260. doi:10.3390/buildings12081260 https://doi.org/10.3390/buildings12081260
- Booth M, Butler JD. A new approach to permit to work systems offshore. Safety Science. 1992;15(4):309-326.
- Kyle, S. R. (1991). Permit to work systems in the offshore industry. SPE Health, Safety and Environment in Oil and Gas Exploration and Production Conference, The Hague (SPE-23240-MS).
- Cann N. Lessons from a permit to work incident. Loss Prevention Bulletin. 2014;236.
- Kołodziejski, M. (2022). Permit to work and risk analysis as an element of safety management systems applied on oil and gas installations. Scientific Papers of Silesian University of Technology, Organization and Management Series, 160, 328-346. https://doi.org/10.29119/1641-3466.2022.160.22 https://doi.org/10.29119/1641-3466.2022.160.22
- Henderson, J. E., Hunter, N., & Embrey, D. (2017). Human factors issues in control of work systems. Hazards 27, IChemE, Birmingham.
- Henderson, J., Burrows, M., & Potts, S. (2019). The treatment of generic task elements in human factors critical task reviews, competence management, and procedures. Hazards 29, IChemE Symposium Series No. 166.
- Bulzacchelli MT, Vernick JS, Webster DW, Lees PSJ. Effects of the OSHA control of hazardous energy (lockout/tagout) standard on rates of machinery-related fatal occupational injury. Injury Prevention. 2007;13:334-338. doi:10.1136/ip.2007.015677 https://doi.org/10.1136/ip.2007.015677
- Karimi B, Burlet-Vienney D, Chinniah Y, Aucourt B. Hazardous energy control on machinery: Understanding the use of alternative methods to lockout. Safety Science. 2019;118:519-529. doi:10.1016/j.ssci.2019.06.003 https://doi.org/10.1016/j.ssci.2019.06.003
- Poisson P, Chinniah Y, Jocelyn S. Design of a safety control system to improve the verification step in machinery lockout procedures: A case study. Reliability Engineering & System Safety. 2016;156:266-276. doi:10.1016/j.ress.2016.07.016 https://doi.org/10.1016/j.ress.2016.07.016
- Yamin, S. C., Parker, D. L., Xi, M., & Stanley, R. (2017). Self-audit of lockout/tagout in manufacturing workplaces: A pilot study. American Journal of Industrial Medicine, 60, 504-509. https://doi.org/10.1002/ajim.22715 https://doi.org/10.1002/ajim.22715
- Karimi B, Burlet-Vienney D, Chinniah Y, Aucourt B. Design of a self-audit tool for the application of lockout on machinery in the province of Quebec, Canada to control hazardous energies. Safety. 2019;5(3):53. doi:10.3390/safety5030053 https://doi.org/10.3390/safety5030053
- Occupational Safety, Health Administration. Permit-required confined spaces (29 CFR 1910.146). U.S. Department of Labor; 2011.
- Health, Safety Executive. Safe work in confined spaces: Confined Spaces Regulations 1997, Approved Code of Practice and guidance (L101, 3rd ed.). HSE Books; 2014.
- Chiu CC, Chang YM, Wan TJ. Characteristic analysis of occupational confined space accidents in Taiwan and its prevention strategy. International Journal of Environmental Research and Public Health. 2020;17(5):1752. doi:10.3390/ijerph17051752 https://doi.org/10.3390/ijerph17051752
- Xia, J., Liu, Y., Zhao, D., Tian, Y., Li, J., Zhong, Y., & Roy, N. (2021). Human factors analysis of China’s confined space operation accidents from 2008 to 2018. Journal of Loss Prevention in the Process Industries, 71, 104480. https://doi.org/10.1016/j.jlp.2021.104480 https://doi.org/10.1016/j.jlp.2021.104480
- Selman J, Spickett J, Jansz J, Mullins B. An investigation into the rate and mechanism of incident of work-related confined space fatalities. Safety Science. 2018;109:333-343.
- Wilson MP, Madison HN, Healy SB. Confined space emergency response: Assessing employer and fire department practices. Journal of Occupational and Environmental Hygiene. 2012;9(2):120-128.
- Suruda AJ, Pettit TA, Noonan GP, Ronk RM. Deadly rescue: The confined space hazard. Journal of Hazardous Materials. 1994;36(1):45-53.
- Burlet-Vienney D, Chinniah Y, Bahloul A, Roberge B. Occupational safety during interventions in confined spaces. Safety Science. 2015;79:19-28.
- Burlet-Vienney D, Chinniah Y, Bahloul A, Roberge B. Design and application of a 5 step risk assessment tool for confined space entries. Safety Science. 2015;80:144-155.
- National Institute for Occupational Safety, Health. Worker deaths in confined spaces: A summary of NIOSH surveillance and investigative findings (DHHS/NIOSH Publication No. 94-103). NIOSH; 1994.
- Fan H, Enshaei H, Jayasinghe SG. Formation of dataset for fuzzy quantitative risk assessment of LNG bunkering SIMOPs. Data. 2022;7(5):60. doi:10.3390/data7050060 https://doi.org/10.3390/data7050060
- Milch V, Laumann K. Interorganizational complexity and organizational accident risk: A literature review. Safety Science. 2016;82:9-17.
- Arumosoye, O. M., & Obriki, O. D. (2022). Conceptual risk pathway model for lifting and rigging operations in heavy industrial construction. Gyanshauryam, International Scientific Refereed Research Journal, 5(5), 346-369. https://doi.org/10.32628/GISRRJ2256237 https://doi.org/10.32628/GISRRJ2256237
- Obogo, S. F., Arumosoye, O. M., & Obriki, O. D. (2020). Conceptual risk management model for heavy lifting and crane installation engineering operations. Shodhshauryam, International Scientific Refereed Research Journal, 3(4), 122-144. https://doi.org/10.32628/SHISRRJ214441 https://doi.org/10.32628/SHISRRJ214441
- Bellamy LJ, Geyer TAW, Wilkinson J. Development of a functional model which integrates human factors, safety management systems and wider organisational issues. Safety Science. 2008;46(3):461-492.
- Bellamy, L. J., Geyer, T. A. W., Oh, J. I. H., & Wilkinson, J. (2008). Safety model which integrates human factors, safety management systems and organisational issues applied to chemical major accidents. Hazards XX, IChemE Symposium Series No. 154.
- Bellamy LJ, Brouwer WGJ. AVRIM2, a Dutch major hazard assessment and inspection tool. Journal of Hazardous Materials. 1999;65:191-210.
- Accou B, Carpinelli F. Systematically investigating human and organisational factors in complex socio-technical systems by using the “SAfety FRactal ANalysis” method. Applied Ergonomics. 2022;100:103662. doi:10.1016/j.apergo.2021.103662 https://doi.org/10.1016/j.apergo.2021.103662
- Skogdalen JE, Vinnem JE. Quantitative risk analysis offshore - Human and organizational factors. Reliability Engineering & System Safety. 2011;96(4):468-479.
- Anderson M. Behavioural safety and major accident hazards: Magic bullet or shot in the dark?. Hazards XVIII, IChemE Symposium Series No. 150, 1-15. 2004.
- Lekka C, Sugden C. The successes and challenges of implementing high reliability principles: A case study of a UK oil refinery. Process Safety and Environmental Protection. 2011;89(6):443-451.
- Choularton R. Complex learning: Organizational learning from disasters. Safety Science. 2001;39:61-70.
- Jacobsson, A., Ek, Å., & Akselsson, R. (2011). Method for evaluating learning from incidents using the idea of level of learning. Journal of Loss Prevention in the Process Industries, 24, 333-343.
- Center for Chemical Process Safety. Guidelines for investigating process safety incidents (3rd ed.). AIChE /Wiley; 2019.
- Center for Chemical Process Safety. Recognizing catastrophic incident warning signs in the process industries. John Wiley & Sons; 2012.
- Birkmire JC, Lay JR, McMahon MC. Keys to effective third-party process safety audits. Journal of Hazardous Materials. 2007;142:574-581. doi:10.1016/j.jhazmat.2006.06.065 https://doi.org/10.1016/j.jhazmat.2006.06.065
- Srinivasan R, Viswanathan P, Vedam H, Nochur A. A framework for managing transitions in chemical plants. Computers & Chemical Engineering. 2005;29:305-322.
- Benjumea JM, Sanchez-Oneto J, Portela JR, Jimenez-Espadafor FJ, de la Ossa EJM. Low power static-heating start-up procedure for supercritical water oxidation plants. Journal of Supercritical Fluids. 2018;135:218-
- doi:10.1016/j.supflu.2018.01.022 https://doi.org/10.1016/j.supflu.2018.01.022
- Zhu, Q. X., Gao, H. H., & Xu, Y. (2017). A survey on alarm management for industrial processes. Zidonghua Xuebao/Acta Automatica Sinica, 43(6), 955-968. https://doi.org/10.16383/j.aas.2017.c170101 https://doi.org/10.16383/j.aas.2017.c170101
- Mustafa FE, Ahmed I, Basit A, Alvi UEH, Malik SH, Mahmood A, et al. A review on effective alarm management systems for industrial process control: Barriers and opportunities. International Journal of Critical Infrastructure Protection. 2023;41:100599. doi:10.1016/j.ijcip.2023.100599 https://doi.org/10.1016/j.ijcip.2023.100599
- Izadi I, Shah SL, Shook DS, Chen T. An introduction to alarm analysis and design. IFAC Proceedings Volumes. 2009;42(8):645-650. doi:10.3182/20090630-4-ES-2003.00107 https://doi.org/10.3182/20090630-4-ES-2003.00107
- Hollender, M., Skovholt, T., & Evans, J. (2016). Holistic alarm management throughout the plant lifecycle. 2016 Petroleum and Chemical Industry Conference Europe (PCIC Europe), 1-6. https://doi.org/10.1109/PCICEurope.2016.7604645 https://doi.org/10.1109/PCICEurope.2016.7604645
- Nagib, A., Munsif, A., & Elsisi, A. (2022). Comprehensive guide to alarm management, rationalization and suppression to achieve optimum situational awareness in the control room. 2022 AIChE Spring Meeting and 18th Global Congress on Process Safety, Paper 64a.
- Venkidasalapathy, J. A., Kravaris, C., & Mannan, M. S. (2019). A quantitative approach for optimization of alarm identification and rationalization. 2019 AIChE Annual Meeting, Paper 66f.
- Kondaveeti SR, Izadi I, Shah SL, Shook DS, Kadali R, Chen T. Quantification of alarm chatter based on run length distributions. Chemical Engineering Research and Design. 2013;91(12):2550-2558. doi:10.1016/j.cherd.2013.02.028 https://doi.org/10.1016/j.cherd.2013.02.028
- Vásquez J, Subias A, Travé-Massuyès L, Jimenez F. Alarm management via temporal pattern learning. Engineering Applications of Artificial Intelligence. 2017;65:506-516. doi:10.1016/j.engappai.2017.07.008 https://doi.org/10.1016/j.engappai.2017.07.008
- Vásquez J, Travé-Massuyès L, Subias A, Jimenez F, Agudelo C. Alarm management based on diagnosis. IFAC-PapersOnLine. 2016;49(5):126-131. doi:10.1016/j.ifacol.2016.07.101 https://doi.org/10.1016/j.ifacol.2016.07.101
- Vásquez-Capacho, J.-W., Perez-Zuñiga, G., Muñoz, Y., & Ospino, A. (2020). An additional layer of protection through superalarms with diagnosis capability. CT&F - Ciencia, Tecnología y Futuro, 10(1), 45-66. https://doi.org/10.29047/01225383.168 https://doi.org/10.29047/01225383.168
- Pariyani A, Seider WD, Oktem UG, Soroush M. Dynamic risk analysis using alarm databases to improve process safety and product quality: Part II: Bayesian analysis. AIChE Journal. 2012;58:826-841.
- Pariyani A, Seider WD, Oktem UG, Soroush M. Incidents investigation and dynamic analysis of large alarm databases in chemical plants: A fluidized-catalytic-cracking unit case study. Industrial & Engineering Chemistry Research. 2010;49(17):8062-8079.
- Liu X, Noda M, Nishitani H. Evaluation of plant alarm systems by behavior simulation using a virtual subject. Computers & Chemical Engineering. 2010;34:374-386.
- Ravikanth, K., Bahuguna, P. C., Glaser, D. C., & Shivalkar, S. (2018). Study of effectiveness of operator training simulators in the oil and gas industry. Proceedings of the 59th Conference on Simulation and Modelling (SIMS 59), Oslo, 79-86. https://doi.org/10.3384/ecp1815379 https://doi.org/10.3384/ecp1815379
- Obriki, O. D., Obogo, S. F., & Arumosoye, O. M. (2022). Advances in workforce safety training models for operational risk reduction. Gyanshauryam, International Scientific Refereed Research Journal, 5(6), 349-382. https://doi.org/10.32628/GISRRJ225638 https://doi.org/10.32628/GISRRJ225638
- Manca D, Brambilla S, Colombo S. Bridging between virtual reality and accident simulation for training of process-industry operators. Advances in Engineering Software. 2013;55:1-9.
- Stanton NA, Chambers PRG, Piggott J. Situational awareness and safety. Safety Science. 2001;39:189-204.
- Sneddon, A., Mearns, K., & Flin, R. (2006). Situation awareness and safety in offshore drill crews. Cognition, Technology & Work, 8, 255-267. https://doi.org/10.1007/s10111-006-0040-1 https://doi.org/10.1007/s10111-006-0040-1
- Zarei E, Mohammadfam I, Aliabadi MM, Jamshidi A, Ghasemi F. Efficiency prediction of control room operators based on human reliability analysis and dynamic decision-making style in the process industry. Process Safety Progress. 2016;35(2):192-199. doi:10.1002/prs.11782 https://doi.org/10.1002/prs.11782
- Health, Safety Executive. Out of control: Why control systems go wrong and how to prevent failure. HSE Books, Sudbury, UK; 2003. Functional safety of electrical/electronic/programmable electronic safety-related systems, Parts 1-7 (Edition 2). International Electrotechnical Commission, Geneva; 2010. Functional safety - Safety instrumented systems for the process industry sector. IEC, Geneva; 2003.
- International Electrotechnical Commission. IEC 61511-1: Functional safety - Safety instrumented systems for the process industry sector - Part 1: Framework, definitions, system, hardware and application programming requirements (Edition 2). International Electrotechnical Commission, Geneva; 2016.
- Hauge S, Onshus T. Reliability data for safety instrumented systems: PDS data handbook, 2010 edition (SINTEF Report A13502). SINTEF; 2010.
- Hokstad P, Corneliussen K. Loss of safety assessment and the IEC 61508 standard. Reliability Engineering & System Safety. 2004;83(1):111-120. doi:10.1016/j.ress.2003.09.017 https://doi.org/10.1016/j.ress.2003.09.017
- Koscielny JM, Bartys M. The requirements for a new layer in the industrial safety systems. IFAC-PapersOnLine. 2015;48(21):1333-1338. doi:10.1016/j.ifacol.2015.09.710 https://doi.org/10.1016/j.ifacol.2015.09.710
- Gabriel A, Ozansoy C, Shi J. Developments in SIL determination and calculation. Reliability Engineering & System Safety. 2018;177:148-161.
- Zhang A, Srivastav H, Barros A, Liu Y. Study of testing and maintenance strategies for redundant final elements in SIS with imperfect detection of degraded state. Reliability Engineering & System Safety. 2021;209:107393. doi:10.1016/j.ress.2020.107393 https://doi.org/10.1016/j.ress.2020.107393
- Liu Y. Optimal staggered testing strategies for heterogeneously redundant safety systems. Reliability Engineering & System Safety. 2014;126:65-71.
- Zhang, A., Hao, S., Li, P., Xie, M., & Liu, Y. (2022). Performance modeling for condition-based activation of the redundant safety system subject to harmful tests. Reliability Engineering & System Safety, 226.
- Brissaud, F., Barros, A., & Bérenguer, C. (2012). Probability of failure on demand of safety systems: Impact of partial test distribution. Proceedings of the Institution of Mechanical Engineers, Part O: Journal of Risk and Reliability, 226(4), 426-436.
- Kumar M, Verma AK, Srividya A. Modeling demand rate and imperfect proof-test and analysis of their effect on system safety. Reliability Engineering & System Safety. 2008;93(11):1720-1729.
- Azizpour H, Lundteigen MA. Analysis of simplification in Markov-based models for performance assessment of safety instrumented system. Reliability Engineering & System Safety. 2019;183:252-260.
- Green, D., & Bell, R. (2017). Proof testing: A key performance indicator for designers and end users of safety instrumented systems. Hazards 27, IChemE Symposium Series No. 162.
- Pastirik, D. (2010). Change management success story: Provisions for carrying out maintenance on safety instrumented systems in a refinery. 2010 AIChE Spring Meeting and 6th Global Congress on Process Safety.
- Alharran D, Nagalingam V, Norazahar N, Ahmad A, Bakhary N, Noh@Seth NH. The survey and perspective of human factors associated with maintenance activity. Journal of Energy and Safety Technology. 2022;5(2):61-69.
- Sheikhalishahi M, Pintelon L, Azadeh A. Human factors in maintenance: A review. Journal of Quality in Maintenance Engineering. 2016;22(3):218-237.
- Sheikhalishahi M, Azadeh A, Pintelon L, Chemweno P. Human factors effects and analysis in maintenance: A power plant case study. Quality and Reliability Engineering International. 2017;33(4):895-903.
- Patriarca R, Ramos M, Paltrinieri N, Massaiu S, Costantino F, Di Gravio G, et al. Human reliability analysis: Exploring the intellectual structure of a research field. Reliability Engineering & System Safety. 2020;203:107102. doi:10.1016/j.ress.2020.107102 https://doi.org/10.1016/j.ress.2020.107102
- Ade N, Peres SC. A review of human reliability assessment methods for proposed application in quantitative risk analysis of offshore industries. International Journal of Industrial Ergonomics. 2022;87:103238. doi:10.1016/j.ergon.2021.103238 https://doi.org/10.1016/j.ergon.2021.103238
- Strand GO, Haskins C. On linking of task analysis in the HRA procedure: The case of HRA in offshore drilling activities. Safety. 2018;4(3):39. doi:10.3390/safety4030039 https://doi.org/10.3390/safety4030039
- Selleck R, Hassall M, Cattani M. Determining the reliability of critical controls in construction projects. Safety. 2022;8(3):64. doi:10.3390/safety8030064 https://doi.org/10.3390/safety8030064
- Energy Institute. Guidance on human factors safety critical task analysis (2nd ed.). Energy Institute, London; 2020.
- Energy Institute. Guidance on human factors safety critical task analysis (1st ed.). Energy Institute, London; 2011.
- Embrey, D. (2010). How to carry out qualitative human reliability assessments in process analyses. 2010 AIChE Spring Meeting and 6th Global Congress on Process Safety.
- Xie X, Guo D. Human factors risk assessment and management: Process safety in engineering. Process Safety and Environmental Protection. 2018;113:467-
- doi:10.1016/j.psep.2017.11.018 https://doi.org/10.1016/j.psep.2017.11.018
- Wang J, Fan Y, Niu Y. Routes to failure: Analysis of chemical accidents using the HFACS. Journal of Loss Prevention in the Process Industries, 75, 104695. 2022.
- Rostamabadi A, Jahangiri M, Zarei E, Kamalinia M, Banaee S, Samaei MR. A novel fuzzy Bayesian network-HFACS (FBN-HFACS) model for analyzing human and organizational factors (HOFs) in process accidents. 2019;132:59-72. doi:10.1016/j.psep.2019.08.012 https://doi.org/10.1016/j.psep.2019.08.012
- Zarei E, Yazdi M, Abbassi R, Khan F. A hybrid model for human factor analysis in process accidents: FBN-HFACS. Journal of Loss Prevention in the Process Industries, 57, 142-155. 2019. doi:10.1016/j.jlp.2018.11.015 https://doi.org/10.1016/j.jlp.2018.11.015
- Wang J, Fan Y, Gao Y. Revising HFACS for SMEs in the chemical industry: HFACS-CSMEs. Journal of Loss Prevention in the Process Industries. 2020;65:104138.
- Li, X., Liu, T., & Liu, Y. (2020). Cause analysis of unsafe behaviors in hazardous chemical accidents: Combined with HFACs and Bayesian network. International Journal of Environmental Research and Public Health, 17(1), 11. https://doi.org/10.3390/ijerph17010011 https://doi.org/10.3390/ijerph17010011
- Zhou, L., Fu, G., & Xue, Y. (2018). Human and organizational factors in Chinese hazardous chemical accidents: A case study of the ‘8.12’ Tianjin Port fire and explosion using the HFACS-HC. International Journal of Occupational Safety and Ergonomics, 24, 329-340. https://doi.org/10.1080/10803548.2017.1372943 https://doi.org/10.1080/10803548.2017.1372943
- Yalcin E, Ciftcioglu GA, Guzel BH. Human factors analysis by classifying chemical accidents into operations. Sustainability. 2023;15(10):8129.
- Wu, Y., Fu, G., Wu, Z., Wang, Y., Xie, X., et al. (2023). A popular systemic accident model in China: Theory and applications of 24Model. Safety Science, 159, 106013. https://doi.org/10.1016/j.ssci.2022.106013 https://doi.org/10.1016/j.ssci.2022.106013
- Wu, Y., Fu, G., Han, M., Jia, Q., Lyu, Q., et al. (2022). Comparison of the theoretical elements and application characteristics of STAMP, FRAM, and 24Model: A major hazardous chemical explosion accident. Journal of Loss Prevention in the Process Industries, 80, 104880. https://doi.org/10.1016/j.jlp.2022.104880 https://doi.org/10.1016/j.jlp.2022.104880
- Obogo SF, Obriki OD, Arumosoye OM. Conceptual model for incident prevention in industrial maintenance engineering environments. International Journal of doi:10.54660/IJMRGE.2021.2.6.847-858 https://doi.org/10.54660/IJMRGE.2021.2.6.847-858
- Obriki, O. D., & Arumosoye, O. M. (2022). Conceptual framework explaining recurrence mechanisms of unsafe behaviors in high-hazard worksites. Shodhshauryam, International Scientific Refereed Research Journal, 5(3), 380-402. https://doi.org/10.32628/SHISRRJ225489 https://doi.org/10.32628/SHISRRJ225489
- Obriki OD, Obogo SF, Arumosoye OM. Review of behavioral safety programs for risk reduction in large workforces. International Journal of Advanced Multidisciplinary Research and Studies. doi:10.62225/2583049X.2023.3.6.6076 https://doi.org/10.62225/2583049X.2023.3.6.6076
- Wolf FG. Operationalizing and testing normal accidents in petrochemical plants and refineries. Production and Operations Management. 2001;10(3):292-305.
- Paltrinieri N, Khan FI, Amyotte P, Cozzani V. Dynamic approach to risk management: Application to the Hoeganaes metal dust accidents. Process Safety and Environmental Protection; 2014.
- Khakzad, N., Yu, H., Paltrinieri, N., & Khan, F. I. (2016). Reactive approaches of probability update based on Bayesian methods. In Dynamic Risk Analysis in the Chemical and Petroleum Industry (Chapter 5). Elsevier, 51-61.
- Di Maio, F., Scapinello, O., Zio, E., Ciarapica, C., Decarli, L., & La Rosa, L. (2020). A multistate Bayesian network for accounting the degradation of safety barriers in the living risk assessment of oil and gas plants. Proceedings of the 30th European Safety and Reliability Conference and 15th Probabilistic Safety Assessment and Management Conference (ESREL2020-PSAM15), 1303-1309.
- Abimbola M, Khan F, Khakzad N, Butt S. Safety and risk analysis of managed pressure drilling operation using Bayesian network. Safety Science. 2015;76:133-144.
- Adedigba SA, Khan F, Yang M. An integrated approach for dynamic economic risk assessment of process systems. Process Safety and Environmental Protection. 2018;116:312-323. doi:10.1016/j.psep.2018.01.013 https://doi.org/10.1016/j.psep.2018.01.013
- Obogo SF, Obriki OD, Arumosoye OM. Advances in continuous hazard monitoring systems for workplace safety. International Journal of Advanced Multidisciplinary Research and Studies. doi:10.62225/2583049X.2023.3.6.6075 https://doi.org/10.62225/2583049X.2023.3.6.6075
- Krishnasamy L, Khan F, Haddara M. Development of a risk-based maintenance (RBM) strategy for a power-generating plant. Journal of Loss Prevention in the Process Industries. 2005;18(2):69-81.
- Hollnagel E, Woods DD, Leveson N. Resilience engineering: Concepts and precepts. Ashgate Publishing, Aldershot, UK; 2006.
- Steen R, Aven T. A risk perspective suitable for resilience engineering. Safety Science. 2011;49:292-297.
- Zarei E, Ramavandi B, Darabi AH, Omidvar M. A framework for resilience assessment in process systems using a fuzzy hybrid MCDM model. Journal of Loss Prevention in the Process Industries. 2021;69:104375.
- Namvar H, Bamdad S. Performance evaluation of process industries resilience: Risk-based with a network approach. Journal of Loss Prevention in the Process Industries. 2021;71:104474.
- Azadeh A, Salehi V, Arvan M, Dolatkhah M. Assessment of resilience engineering factors in high-risk environments by fuzzy cognitive maps: A petrochemical plant. Safety Science. 2014;68:99-107.
- Shirali GA, Motamedzade M, Mohammadfam I, Ebrahimipour V, Moghimbeigi A. Challenges in building resilience engineering (RE) and adaptive capacity: A field study in a chemical plant. Process Safety and Environmental Protection. 2012;90:83-90.
- Zinetullina, A., Yang, M., Khakzad, N., Golman, B., & Li, X. (2021). Quantitative resilience assessment of chemical process systems using functional resonance analysis method and dynamic Bayesian network. Reliability Engineering & System Safety, 205.
- Chen C, Yang M, Reniers G. A dynamic stochastic methodology for quantifying HAZMAT storage resilience. Reliability Engineering & System Safety. 2021;215.
- Jain, P., Pistikopoulos, E., & Mannan, S. (2016). Using resilience principles for prediction of loss of containment events in batch operations. 2016 AIChE Annual Meeting, Paper 682b.
- Costella MF, Saurin TA, Guimarães, L. B. de M. A method for assessing health and safety management systems from the resilience engineering perspective. Safety Science. 2009;47(8):1056-1067.
- Misuri A, Ricci F, Sorichetti R, Cozzani V. The effect of safety barrier degradation on the severity of primary Natech scenarios. Reliability Engineering & System Safety. 2023;235.
- Zhu S, van Jaarsveld W, Dekker R. Critical project planning and spare parts inventory management in shutdown maintenance. Reliability Engineering & doi:10.1016/j.ress.2021.108197 https://doi.org/10.1016/j.ress.2021.108197
- Obetta PC, Ninduwezuor-Ehiobu N, Olisakwe HC. A CMMS-based concept for optimizing preventive and corrective maintenance of static mechanical equipment. International Journal of Engineering and Modern Technology. 2023;9(3):287-319. doi:10.56201/ijcsmt.v9.no3.2023.pg287.319 https://doi.org/10.56201/ijcsmt.v9.no3.2023.pg287.319
- International Association of Oil, Gas Producers. Asset integrity: The key to managing major incident risks (Report No. 415). International Association of Oil and Gas Producers; 2008.
- Ogunnowo EO, Adewoyin MA, Fiemotongha JE, Igunma TO, Adeleke AK. A conceptual framework for reliability-centered design of mechanical components using FEA and DFMEA integration. Journal of Frontiers in Multidisciplinary Research. 2023;4(1):342-361. doi:10.54660/.JFMR.2023.4.1.342-361 https://doi.org/10.54660/.JFMR.2023.4.1.342-361
How to cite